Cost break up sheet ( per operation cost )
Cost break up sheet
To find the cost of any operation
We should know about the various factors that are indulged to complete a specific type of operation
Here is a list of factors that specify the cost of a particular type of product
1. Cost of machine on which we have to prepare our product
2. Life span of the machine so that we can calculate the depreciation value of the machine
3. Production rate of the machine
4. Area in square feet which is being used to complete that operation.
5. Rent of that area per square feet.
6. Unskilled labour wages in that area.
7. Number of unskilled workers working there to complete that operation.
8. Skilled manpower wages in that area.
9. Number of unskilled workers working there to complete that operation.
10. Power charges in that area
11. What is the machine power consumption rate ?
12. What is the power consumption per minute, per hour, per shift, per day, per month and per year ?
13. What other electrical appliances like light, fan etc are being used to run that machine and to complete that specific operation.
14. If there are other factors that effects the cost of operation , you can them also in the list.
so by considering all these above factors, we can calculate the price incurred to perform a specific operation.
Let us understand with the help of an example
Step 1 To calculate the Number of strokes per year
Let us assume Strokes per minute as 9
Strokes/Day will be
@21.8 Hrs/day,3 shift,90% efficiency,300 days
= 9 x 60 x 21.8 x 0.9 = 10594.8 or 10594
Strokes/Yr-3 shift of 8 Hours@90% efficiency 3178440
Step 2 To calculate the Cost of machine per year
Let us consider Cost of Machine as Rs 5500000
And Life span of M/c in Years 10
So the cost per year of machine considering depreciation will be
= Rs 5500000/10 =Rs 550000
Step 3 To calculate the Area Cost per year
Let us consider Area in Sq. Ft on which machine is fitted as 107.63
Extra Ares(30%),Sq. Ft 32.3
Then Total Area will be = 107.63 + 32.3 = 139.9
Area Cost/Yr@ 7 Rs/Sq.Ft,Rs =139.9 x 7 =11753.2
Step 4 To calculate the Manpower cost per year
Let us consider that one direct manpower is working for that operation
Direct Man cost/Yr@5000/Mth-CTC,for 3 Shifts
= 5000 x 3 x 12 = 180000
Let us consider that one indirect manpower is working for that operation
InDirect Man cost/Yr@4000/Mth-CTC,for 3 Shifts
= 4000 x 3 x 12 = 144000
Total Manpower cost/yr,Rs = 180000 + 144000 = 324000
Step 5 To calculate the Power cost per year
Let us assume Power of M/c in Kw 28
Power cost/Yr@Rs 6/Kw and 20%load factor
= ( 28 x 6 x 300 ) + ( 28 x 6 x 300 x 0.2 ) = 1098720 + 219744 = 1318764
Step 6 To calculate the overhead cost per year
Overheads@10% on total costs = (550000 + 11753.2 + 324000 + 1318764) x 0.1
= 2204217.2 x 0.1 = 220421.72
Total costs/Year = 2204217.2 + 220421.72 = 2424638.92
Stroke Rate- in Paise = 2424638.92 / 3178440
=Rs 0.77